First Production Units Arrive

October 27, 2014 in 8 Channel PDU by Joshua Oster-Morris

The first production units arrived from the Florida factory this afternoon. So far, all the units I’ve tested are working electrically. Two were mishandled during the encapsulation process and are too funky to let out of the lab. The will be used for testing. Before these first units go out the door, I will be updating the firmware on all the units and doing a burn in test.

I will be setting up a system for doing commerce in the coming days. The days after Motobrain hit the market are almost here.

BC2616BE-A31D-4189-AA42-C64A4F89A176[1]